Rönne River Catchment
In RRC, the proposed action plan lead to the establishment
of a working group consisting of representatives from the key
municipalities in the catchment and one representative from the
agricultural sector, with the aim to coordinate actions and find
financial resources for the proposed plan (Galaz, 2005). However,
the attempts did not lead to new institutional arrangements or the
realization of the project. According to the consultancy (Interviewee
4, Personal Communication) a lack of leadership to operate the
new action plan, and a lack of consensus to invest in the project
among the representatives in RRC contributed to that the plan
was never realized. This is also consistent with Galaz (2005) who
argues that a lack of interest from the industries and some of the
high-polluting municipalities in RRC hampered the development
towards the fulfilment of the new management plan. Hence, the
willingness to invest in implementing the common water quality
plan as in Kävlinge River Catchment was weak in RRC. Moreover,
the organizational structure of Rönne River Committee remained
mainly unchanged despite the altered scope and planned activities