When B is of the opinion that the Works are Substantially Complete, B shall submit to A a written request of inspecting the Works so as to determine whether Substantial Completion has been achieved. Upon such request, A must respond within twenty five (25) days of its receipt with either (i) a Certificate of Substantial Completion or (ii) an explanation of the reasons why the Works are not Substantially Complete, including a list of open items necessary to achieve Substantial Completion (Outstanding Works). A shall advise B of the time reasonably required to complete Outstanding Works., which shall be no more than two (2) months.
request of inspecting
Outstanding Works