Bidder Qualification:
1. The Bidder shall have a past and present reference regarding products, machinery, installation, and
any related equipments that have a similar or same size of machinery or equipment as proposal and
must be recognized in the sugar industry.
Time of Delivery:
st
- The onsite fabrication and installation work shall start not later than 1 September 2015
st
- The finish date of equipment installation work shall not later than 1 November 2015
th
- The testing and commissioning shall be perform during 15 November 2015
th
- The factory commercial operation date are fixed on 30 November 2015
Submittal the Proposal Document:
The bidder shall submit 2 copies of proposal document, one mark “Original” and “Copy” for other. Each
copy shall divide into 2 seal envelopes as follows:
Envelope 1 shall contain commercial proposal, include:
1. Price proposal
2. BOQ of piping system and pump installation works
3. Term of payment and commercial condition
4. Warrantee period
Envelope 2 shall contain technical proposal, include:
1. Scope of works and limitation of supply
2. BOQ for piping system and pump installation works
3. Work schedule
4. Pipe and pipe fitting specification sheet
5. Material vendor list and material certification
6. Project reference
The quoted price shall be fixed and not subject to change, escalation and revaluation. The validity
period of this proposal is not less than 120 days from the submittal date. In addition, Thip Suphanburi Bio
Energy Co., Ltd. (or the project owner) shall reserve the right to change any conditions or not to consider the
bidding document of any bidder.
The Proposal shall cover design, supply or fabricate, insurance, transportation to site, installation,
commissioning, testing of all works related to equipment supplied by contractor including supervision of