Dry boring methods employ the use of a temporary casing to seal the pile bore through water-bearing or
unstable strata overlying suitable stable material. Upon reaching the design depth, a reinforcing cage is introduced,
concrete is poured in the borehole and brought up to the required level. The casing can be withdrawn or left in situ.
Dia. 0.35-0.60 m. is conventionally used.