Dear Andy and all concerns,
RE : Box Endeavour v. 10N (delay)
Original schedule : Etd Lcb. : May 22
Since HASCO(the carrier we are using) shares the allocation with Zim Line who is the owner vessel of Box Endeavour.
We hv checked the situation directly to (Zim), this vessel hs dry dock(repair) and delayed from Hochiminh before sailing to BKK.
Box Endeavour 10N has departed HCMC since May 18 and she should arrive BKK around May 23.
It hs been facing continuous delay, and here is the information as of today….(May 27th)
Berth Bkk : May 27 (23:45 hrs)
ETD/Bkk : May 30
ETA/Lcb : May 31
The huge delay caused by the following reasons : -
1. Delay from Hochiminh (vssl dry dock)
2. The lower tide level problem at BKK/PAT.
3. Port congestion at BKK caused by gantry crane damaged problem, and terminal 20F hs stopped operating.
FYI, BKK/PAT operates 2 terminal (ter1 & ter2), both terminal hs only 2 gantry cranes each.
Due to continuous delay problem, Hasco & Zim Line will not issue their official delay notice until they could fixed the exact eta/etd Lcb.
They just report the daily updated information by email.
We really regret for this uncontrollable event and understood how much trouble caused to you.
Anyway, it’s out of our control, and hope for your kind understanding.
We will keep you updated the situation from time to time and once we get the official notice fm shpg line, we will send to you.
Kindly wait.
Thank you.