Reserves are dollars included in a cost estimate to mitigate cost risk by allowing for future situations that are difficult to predict
Contingency ความบังเอิญreserves allow for future situations that may be partially planned for (sometimes called known unknowns) and are included in the project cost baseline
Management reserves allow for future situations that are unpredictable (sometimes called unknown unknowns)