Dear K.Supitcha krub,
As per POB plan of Funan has changed to defer heat tracing project by 1 week, so I would like to revise the project execution plan as following:
16-20 Apr’15: 2 POBs for site survey job batch 1
23-27 Apr’15: 2 POBs for site survey job batch 2
28 Apr’15: Start ship out the fabricated material for batch 1
1-21 May’15: 10 POBs for insulation installation work
Could you please help confirm whether you can follow this plan or not krub.
Sorry for making you inconvenience krub.