Dear Khun Yim and dwp team
Thank you for your information and more perspective design provided to us for making decision.
As we discussed about project scheduled that should be ready to use within Dec-15,
if we awarded dwp team for design consultancy phase, we need to confirm for the timeline and process via below ka.
- Project kick-off and briefing for final requirement : 1-2 days
- Conceptual design development : 7-10 days (Within 23 Sep 15)
o Please provide 5 conceptual design for an option to make decision by top management.
- Conceptual design feedback and comment by top management : Friday 25 Sep 15
- Final conceptual design : Within 30 Sep 15
- MEP design and construction documentation preparation for bidding : 1-2 weeks
If schedule as per above, need to confirm from your team that you can follow by this or not?
If you have any guidance or consideration, please feel free to let us know ka.