Regarding the New GM Line (CYT Project) as per attached PO from MKK.
This moment still waiting customer confirm schedule for commissioning work.
The staff of MKK Mr.Apirapun informed me about July but until now not response.
Please help me to confirm schedule? Mr.Isumihara to take care this project?
Because the remaining issue invoice 10% for HP16-MKKA-02031_Instrument & 100% for HS16-MKKA-02032_ Engineering Fee (commissioning)