Sorry for postponing. Please kindly learn the reasons why we postpone and we are really hurry to solve.
1. We’ve been starting the work since early June and we’ve been keeping negotiate the testing plan with AIS until now;
2. AIS told all the vendors that they wanted all vendors to stop their work on the July 2nd and everyone cannot do test until AIS says yes;
3. For the reason 2, we had to wait for nearly 1 month. We have been keeping contact with AIS, and 2 weeks ago AIS said they would help us to do the test but they need a E-mail from NSN to empower TTT to be the deputy of NSN first or they cannot do any help;
4. After that, we sent a E-mail to K. Cholapan that NSN needed to write a E-mail to AIS and empowered TTT to be the deputy of NSN;
5. AIS said they were not still receive any empowering E-mail from NSN, so we need NSN to write a E-mail to AIS as soon as possible