As per discussed for CCS installation the piping progress very low, Almost site obstruction are scaffolding and steel structure (support pipe) not be continues installation and hand over back to piping.
Piping side found obstruction by shortage materials and isometrics drawing with “HOLD”, Which the isometric drawing with “HOLD” we are just double joint and can’t to issue progress in the official report ( Roughly work front 1,350 DB Appox. Between Column BO-BF on Pipe Rack ), However the obstructed details please be seen as the e-mail below and report attached.