Following the assignment of mitigating actions, XXX stakeholders derived new values of
severity and likelihood for the risk with these mitigating actions in place following the process
described in previous sections. These revised risk values were then evaluated for the assignment
of mitigating actions following the process described above. If a revised risk value was deemed by
XXX stakeholders as requiring further mitigation, actions would be assigned with the risk value
being revised once more. XXX stakeholders would repeat this process as long as the risk value
was determined to be unacceptable.