INVESTMENT IN INFRASTRUCTURE
Every successfully commissioned infrastructure adds
to the reliability and resilience of Singapore’s power
network and on this front, SP is constantly upgrading
and expanding its operational infrastructure. The year
saw good progress made on major 400kV and 230kV
projects, while new projects and network planning
initiatives were started.
Several major 400kV, 230kV and 66kV Transmission
Projects were commissioned. They include:
• The Rangoon 400/230/66kV Substation will cater to
a growing demand for power and strengthen the
network in central Singapore.
• The Tembusu 230/66kV Substation will serve as
an additional primary source to meet increasing
load demand in Jurong Island, which is home to
leading petroleum and petrochemical industries,
and improve the fault level margin for more
generation connections.