• 22 kV switchgear at substation A and 22 kV distribution cables from substation A to substation G shall be kept in SUPPLIER’s Scope of supply.
• Relocate the 22 kV distribution cables from substation A to new substation refer as attachment #1 Overall Plot Plan.
• 6.6 kV switchgear, 22/6.6 kV transformer and 6.6 kV power cables from transformer to the 6.6 kV switchgear at substation B shall be deleted from SUPPLIER’s Scope of supply refer as attachment # 2 Simply Single Line Diagram.
• Low voltage power shall be supplied from new substation instead of substation B