The revision of MMRP1-TI-ASEC-UHA-0100 must be "B" because the latest reply from EGAT with "EN" status was done on the revision A. -MMRP1-D-ASEC-UHA-0301 has no longer need to be submitted to EGAT's Engineering team since it was already received "NE" status but the document shall be stamped "Final for Construction" and submitted to EGAT's construction team