Please co-ordinate directly with me on work sequence as there is mixed messages from Head Office.
1. It is critical that you complete the Membrane footings.
2. Please complete Building 1, 2 and 3 corridor decks
3. Please issue the Cost for the Pool Deck - Beach Society
I am worried very little progress on the Membrane footings has occurred over the last 2 days. I have met with your manager and engineer and the meeting concluded with an agreed solution. We understand the removal of the concrete from the beam (clash of beam and HD Bolts) is additional work.
Please do not leave site without completing items above.