Dear all
Minutes meeting Grey recycle PPE#2. Shutdown planed PPE#1 on 26 Oct 2015 – 06 Nov 2015.
Mechanical field work on progress install and fabrication follow plan (Grey unloading, Grey hopper and platform ) .
- Grey vacuum pump for grey weighing ongoing to install on platform, K-Tron platform delay from plan.
- Solenoid valve, sensor and instrument follow list of Dhawath not done delay from plan.
- Adjust mechanical field work plan in shutdown planed must be done before 5/11/15.
-
Electrical field work on progress install cable of control system follow plan.
- Control systems of divertor valve grey grinder and grey unloading ongoing to install.
- Control systems of grey weighing sequence will simulator present in week42.
- Date 28/10/15 Main electric mixing PPE#2 shutdown 8hr for tie in main electric supply to grey control panel