Note that J587 already completed and remaining only some man still on this job.
J620 already started at Yard 6.
Other jobs such as yard improvements like B-001 to B-007 is been carried out at moment.
Report do not show what the manhours are used for. To report that manhours are used for J587 is completed not correct for months already. However, I do not think this information are not able to get from your side as well.