Dear all,
Please note that our VO assessment with subcontractors shall always only refer to the approved PMI document, which is the sole document showing the scope of the additional work ordered.
Hence, additional work items, which are not shown on the approved PMI document but shown on the shop drawings, are treated as proposal by the subcontractor only, and shall NOT be accepted and included as VO in the assessment.
If the subcontractor want to claim the additional work items as variations, they shall request the Site Team to cover the additional work items by new PMI for head office approval again.