However, in the event that the selected supplier of a major purchase (or critical
item) is not on the above list, the Senior Manager/Project Manager shall arrange for the capabilities of the supplier to be checked, and a Supplier Assessment Report to be prepared. Confirmation of the order will be dependent upon a satisfactory assessment