Khun Phadai,
Total Equipment is 17, out of that 3 we have sent for signing and balance already signed
Total Piping Test Pack is 71, out of that 63 TP we have sent for signing, 4 TP already signed and balance 4 TP no Insulation
No Insulation TP is 1. ERD-003
2. ERD-004
3. ACH3-001
4. ACH3-002
There have some additional piping also but don’t have pre commissioning check list sheet
We need to make report for additional piping ?
Regards,
Salim