Dear K.Kanet
Refer to chiyoda team visited to Daiwa with colon on yesterday (16/Nov/15) . I would like to inform schedule for improvement for this problem detail as below,
1. 17/Nov/15 - You inform to me on morning time actual stock (Old lot) at Colon q’ty = 14,000 Pcs. and stock at Chiyoda (Old lot ) q’ty = 3,000 Pcs.
2. 17/Nov/15 - Our supplier will update and revise WI for this process and then produce sample new lot after improvement process.
3. 18/Nov/15 - Chiyoda will be receive sample for new lot from supplier and will check all condition at our factory.
4. 19/Nov/15 - If Sample new lot approved Chiyoda will inform to supplier for produce mass production.
5. 24/Nov/15 - Chiyoda will delivery replacement to Colon total q’ty 17,000 Pcs.
Please kindly review our schedule.
If we have update any information I will inform to you as soon.