• This project must be finish on May’16 but now we found the project will be delay because customer not confirm approved the platform drawing to ours, therefore this project Will be postponed and customers aware with this problem.
• We must be using total 30 day for work,
- 14 day for fabrication the platform at factory of subcontractor.
- 2 day for testing the platform witness by MSS and YTH
- 14 day for install new platform at site and install the sample probe, Opacity , pulling sample line for CEMs, pulling the power and signal cable from stack to Analyzer house.