As we are inspected with CRC, PPS and PAL on 11th May 2015 regarding acoustic between brick and façade mullion that proceed by PISA as reference that delay and doesn’t’ have some detail of hotel façade don’t clarify and effect with hotel interior work.
Therefore, we agreed and concluded that request to hotel construction work instant PISA, to appropriate and doesn’t affect the hotel interior work. We enclose the detail of guestroom cladding as above and the detail of work that PISA processed for your information to instruct hotel construction contractor.