19. A serious incident has occurred. The assigned solution team is unable to resolve this incident within the agreed time.
The Incident Manager is called in.
Which form of escalation describes the above sequence of events?
Formal escalation
Functional escalation
Hierarchical escalation
Operational escalation
Answer: C