I explain about situation of these 3 months unpaid it as below;
1. In Jan -13 : Result of Waste Water that the over standard form Phase 9/2. I call Mr. Peerapong ( PIP Staff) to meeting this problem. Meeting of conclusion mistake form Waste Water System of W/H Rent that is responsible by PIP.
2. In Mar, Jun-13 13 : Result of Waste Water that the over standard form PLC. The reason that we don’t unpaid;
2.1 PLC is new W/H.
2.2 We want to test run the Waste Water System, that it don’t smooth.
2.3 We want to find root cause , take action and find corrective action with Kajima.
2.4 We prepare plan to clean it by Kajima advised.
2.5 We will prepare letter to PIP, that lessen the indulgent pay these claim.