Thanks for your phone call yesterday.
As per original production lead time is 52 days after order confirmed, today we
further negotiate with factory and finally can rush for 40 days production lead
time.
This item is made of acrylic and during production all hand-made polished piece by
piece, so 40 days really the best production lead time for 6000pcs.
Is it possible that you could confirm order and make 30% deposit within tomorrow and
also send us a TT copy tomorrow, so that we can arrange the order to factory
tomorrow to have more time.
As Oct 1 to Oct 7 is public holiday here in China, will resume working on Oct 8.
Awaiting for your news.