1. Have you applied Section 12 for Outer ring of both 2G and 3G HUB.
As informed in the telephone meetings several times (maybe in Japanese), you can use
1. We noted that you are waiting for internal command for O/R of 2G.
I will check with Sogahara san.
As to O/R of 3G, noted. Has it been approved? Or, still waiting for the approval?
2. Re-import of O/R of 3G
Please confirm it is MAY 2014 i/o 2015.