In previous versions of MSProject you could delete the task and try to compare the schedule and costs before and after, but you’d have to re-enter all of the task and resource data again.
In Project 2010 Professional, all you have to do is Inactivate the task. The purpose of this feature is to help answer the “What If” question with the least pain possible.