Dear K. Eakapon,
The below is the agenda of Lamberet , could you please check with landlord as following :
a) Lamberet will be allowed to drill the ground to anchor the legs of the POD box. It’s altogether 120 holes, diameter 24 mm.
b) Lamberet will need power 380V and 220V, and access to toilet,
c) Lamberet need authorisation to work off-hours (until 10 p.m.) so that they can complete in 3 days.
d) They need the landlord to install a water outlet beside the fresh transfer box as well, This will be for cleaning the transfer station and cleaning in side the boxes of vehicles
Tentative date of POD box to be installed in Saraphi around 27th – 30th Jan , 14
Regards,
Rodsak Kongsakul