According to information from Procurement Dept. told me that “Main COP of FL1,P3-4” will be arriving at Site on 16 Nov, 2016 09.00 krub.
Please kindly prepare Tester and Installer Team for replacement and then planning for Load Testing on the Wednesday afternoon.