Kun Chat,
Thanks for the update quote.
1. Please start working for detail design work and submit it to Monsanto for review and Approval.
2. Please submit the overall project schedule to us in MS project format.
3. Please also send us your plan / schedule for equipment mobilization, this need to be informed 3 days in advance in order that our team can prepare the site. All equipments have to be in a good condition / safe for operation and must be a standard equipments / tools.
4. Please also send us your plan / schedule for man power mobilization, all you project team (project manager, supervisor, safety office and workers) will need to attend safety orientation / Pre job activities and compliance review prior to start working on site. Please also provide us project organization chart, which show their name, role / position and their contact number (for Manager and supervisor level only).
5. You will also need to provide the following prior commencing the work on site:
a. Company Policy Statement document
b. Medical Services and First Aid kits
c. Injury/Illness Reporting
d. Hazard Communication
e. Personal Protective Equipment
f. Fire Protection and Prevention
g. Hand Tools
h. Employee Safety Training documentation
i. All others that apply to the specific type of work performed by the contractor
6. Again, please read and understand Monsanto ‘ES&H Section 5’ and ‘site condition – General’ and share it to all your team member in order that they are all understand Monsanto ES&H requirement.
Appreciate if you can send the above information within this week and if you have any question, please do not hesitation to contact us.
Rgds
Ridwan
Kun Chat,
Thanks for the update quote.
1. Please start working for detail design work and submit it to Monsanto for review and Approval.
2. Please submit the overall project schedule to us in MS project format.
3. Please also send us your plan / schedule for equipment mobilization, this need to be informed 3 days in advance in order that our team can prepare the site. All equipments have to be in a good condition / safe for operation and must be a standard equipments / tools.
4. Please also send us your plan / schedule for man power mobilization, all you project team (project manager, supervisor, safety office and workers) will need to attend safety orientation / Pre job activities and compliance review prior to start working on site. Please also provide us project organization chart, which show their name, role / position and their contact number (for Manager and supervisor level only).
5. You will also need to provide the following prior commencing the work on site:
a. Company Policy Statement document
b. Medical Services and First Aid kits
c. Injury/Illness Reporting
d. Hazard Communication
e. Personal Protective Equipment
f. Fire Protection and Prevention
g. Hand Tools
h. Employee Safety Training documentation
i. All others that apply to the specific type of work performed by the contractor
6. Again, please read and understand Monsanto ‘ES&H Section 5’ and ‘site condition – General’ and share it to all your team member in order that they are all understand Monsanto ES&H requirement.
Appreciate if you can send the above information within this week and if you have any question, please do not hesitation to contact us.
Rgds
Ridwan