Refers to the Guideline for Estimating (THAG380) to select the technique of estimating
effort. Available effort estimating techniques include:
– Top-down. It is usually based on previous similar projects, and includes the effort of
all functions within project.
– Bottom-up. Each task of project in WBS is separately estimated and the results
aggregated to produce an estimate for the overall job.