This paper presents result of study to develop micro hydro
plant at village of Sambangan, one of many typical villages in
Bali where part of its population still has no have access to
electricity. The study covers technical assessment of the hydro
power of the Tiying Tali river which passes nearby the village.
It also followed by analysis on costs involved such as civil,
mechanical, and electrical works. The study also identifies
local manpower to operate and maintain the power plant so it
can be utilized effectively and sustainably