As discussed with Khun Preecha yesterday, the project queries process will be as below:
1) On site, M&E technical queries will be checked and prepared by Khun Songkran, who will confirm with Khun Preecha and centrally coordinated and issued by Khun Krittanan as RFI.
2) Building including ID work technical queries will be checked and prepared by Khun Witoon, who will confirm with Khun Preecha and centrally coordinated and issued by Khun Krittanan as RFI.
3) For Tender Queries, M&E tender queries will be checked and prepared by Khun Siranee and Khun Veera. Information shall be passed to Khun Songkran who will then help to check the English and coordinate the issuance via process 1) above
4) Building including ID work tender queries will be checked and prepared by Khun Pontip and Khun Chitavorn. Information shall be passed to Khun Witoon who will then help to check the English and coordinate the issuance via process 2) above
5) Khun Preecha and Khun Krittanan will coordinate the weekly RFI report for chasing the queries from consultants.
This process will be effective for new tender queries from today. Thanks.