4. The issuing department of this clearance certificate should be
informed immediately after de-energising / re-energising the
equipment. However, permission for any activity on the isolated
equipment shall be granted by the Operation-In-Charge only after
Authorised Person of Electrical Operation returns the original
certifying job completion.
5. Switching off and isolation of space heater circuit shall be
mandatory along with de-energisation of a motor unless specifically
requested in writing by Electrical Maintenance to keep it ON.