CAUTION – Testing at excessive pressure or for excessive time may
damage the piping system.
When testing at system design pressure or less, test duration including time to pressurize, time for initial
expansion, time at test pressure and time to depressurize should be limited to a practical time period given that
the test section is not to be left unsupervised at any time during leak testing.