This was a very straightforward presentation/meeting, starting by Mr. HONG questioned to Thai TODA as follow:
1. What was your design based on? Based on YLTH plan.
2. Turn-key VS BOQ price
This project is the turn-key type. This means if cost up in a case of piling required greater in length, increasing amount will be responded by TODA.
3. To be provided pile specification
4. Layout will be changed:
- Design If design changed and affects to construction cost, not over 10% will be applied the proposed price.
- Yusen will provide more details if change needed