The attached file is the preparation schedule of the first lot of production planning which contained 3 sheets as following.
1. Sheet name “Preparation and Production time” define the date of placing order for Raw materials /Pack materials please fill in the details date and quatities, some materials I already fill in .See the red font that concerned with the production to fill in.
Production please consider how feequency to deliver the RM/Pack Mat.
In the subject no. 8 , QC please consider whether it ‘s possible or not.
2. Sheet name “PD Manpower and time in-out” , it is the man power /equipment/working time and other information which necessary for production please fill in. Some information I already fill in as base on the cost calculation.By the way , K.Aoki informed that the Pallet quantities might not enough due to we have only 140 pallets then I inform k.Chu to find the Rental supplier pallet.K.Sila please fill in /following.
3. Sheet name “RM Lead time” , Chu please fill in the lead time for us.
We will present all the information on 11st May 2015 at 2:00 pm , each department please fill in and send back to me within this Friday especially Factory Dept information.