Without basic change, the optimum procedure (Appendix D) was used for
174 demonstration runs. The proces's was actually carried out over a
period of ten months. The wastes of the regeneration plant were
processed routinely with the optimum procedure. Brine was processed,
a product was returned for use, and salts were prevented from entering
the environment.
During the last month of the project, the equipment was in use under
the control of non-professional personnel of the regeneration plant.
There were no reports of difficulty with their operation. It would
seem that the process lends itself to operation by non-technical
personnel.
Appendix G is a record of the operation throughout the demonstration.
Complete data for each run is recorded: data sheets for each run are
included in Appendix G. These runs provide data which show the
following