Despite the fact that there were numerous variation work (as listed in item B below) issued by your team between the period of April & May 2016, you have requested us to assist and expedite the work during the weekly site meeting that we have had with you, to meet the date of the opening of the mall i.e. 29th May 2016 but on the other hand failed to review and grant us a revised completion date under this situation