Internal Traffic Control Meeting with JV 19 July 2014
Statement: Every construction area will require warning signs and/or traffic control.
This must be planned and notified to all relevant parties.
1.Planning
a.Based on the 2 week look ahead a 1 week traffic control plan shall be made.
b.Agree typical layouts with DOH Consultant for all potential situations.
c.Revise traffic control drawings for specific locations as per point ‘b’ above.
d.Internal meeting every Friday morning to finalise the plan for next week.
e.Issue notification letters with attached location list and detailed drawings to DOH, SDAO, Police and Community Leader.
f.This will start from 25th July 2014.