Regarding Purchase Order
1. Please do not release PO to suppliers without authorized signature.
2. If have any Revision on PO must be sign by BOSS before material delivery.
3. Partial delivery will not be acceptable. If have any changes should be revise according before delivery (i.e. one PO one Delivery)
Regarding Suppliers
1. Material Delivery must be with approved PO copy.
2. Delivery documents must have mentioned PO No.
3. Changes in Quantity, quality & specifications must be cleared by suppliers to purchase by prior notice/before material delivery.
4. Material must be delivered up to 15:00 - 16:00 o’clock.
Regarding Purchase Request
1. Any changes/cancellation on PR must be notified by e-mails.
Regarding Repairing Material
1. Supplier must come with approved item checking.
2. It must be time period for material checking. ( we have huge list of pending materials)