Part 2: Launching of the 1st “Save 50%” campaign in Wieng Nua and Pha Bong
Activities Responsible Agency
a) Consultation meetings PEO and TAOs on strategy and procedures of awareness building activity PMU
b) Design and production of campaign materials: leaflets, etc. PMU
c) Procurement of ICS from Chiang Mai PMU
d) Production of ICS ICS Producer
e) Issuance of QC sticker to ICS product DEDE
f) Transport ICS from Chiang Mai to MHS PMU
g) Program execution at Wieng Nua TAO (half day) and Pha Bong TAO (half day) TAOs, PEO, PMU
h) Reporting PMU
i) Follow up feedbacks/ impacts from new ICS users TAOs, PMU