Dear whom it may concern,
HMMT requested KIT to prepare the document as below:
1) PC/KIT confirm quantity of pallet for TMAP review cost and directly contact with K.Tada PA/HMMT for confirm packing Std.
2) Press Engineer/KIT issue BL material size and send to PS/HMMT on 13/1/16
3) QA Engineer/KIT issue PCR and send to HMMT on 18/1/16
4) Welding Engineer/KIT issue OP and send to HMMT on 18/1/16
Progress information:
-Volume refer 15 ARP from HMMT
-Tooling of KIT for Die, Jig, CF finished
-HMMT will confirm component Plug seat part no.90080-34017 to MKG/KIT for sourcing
-HMMT target finish HVPT on E-Mar’16 by TMAP will confirm SOP to all suppliers in advance 2 months