Financial applications in particular are subject to extended parallel tests to ensure that the organizations records will not be compromised in any way by the installation and
implementation of the new product. It is common to run for several weeks to a full quarter in parallel before the decision is made to move to production. This can place a significant burden on the operations staff and they must be a full participant in the parallel planning process. It can also dictate the possible implementation dates for the project.