The sequence of events leading to the incident began early in 2009. Starting from January to March when three months to repair the turbine unit 2 was completed which included better control of speed regulation. Turbine has synchronized back to the grid on March 16. However, the turbine wheel is not properly balanced again after the repair has been completed. The unit 2 turbine is taken offline (stored in reserves) until August 16, 2009.