Zeon Chemicals (Thailand) Co., Ltd build new Tank Farm Area of Hydrocarbon Resin Production Project. The packing of hydrocarbons 4 atoms consists C4 Monomer Tank are 92 cubic meter (capacity use 78 cubic meters) of 2 tank and C4 Raffinate are 52 cubic meter (capacity use 44 cubic meters) of 2 tank. Which is C4 Raffinate non-reactive hydrocarbons 4 atoms from the refining process and is a byproduct of the project, storage tanks C4 Monomer connecting the new storage tank Into the tank and the reaction of the production line 1 and 2 and piping transportation C4 Raffinate between Distillation Column to new tank returned to of IRPC Co,. Ltd with legal requirements that determine the distance of a storage tank with built side by the Ministry of Energy.
The new tank construction yard activities during May-June, 2015 present construction yard new tank completed.