Today activities updated.
Generator Diesel Leak issues, Fixed by Generator Engineer today with O-Ring and Seal with Tape.
I enclosed the pictured show our operation. We will monitor it for a week to confirm this method success.
Basket Tray, 80% completed. The remaining 20% need to wait for Rack Cabinet installed to ensure perfect location and tray plug into Rack Cabenet.
The schedule remain almost the same of all project activities. Just add 1 day to finish 20% of Basket Tray on next Thursday.