hi,Suwannee , Piyachart :
it looks quite urgent for now . Can u share with me the background .
PO no.04-1-173/15 ETA date on May 22 , 2015 instead what is the 1)original ETA requested by Neo and what is their respond of 2) confirmed ETA
PO no. 04-1-174/15 ETA date on July 03 , 2015 instead what is the 1)original ETA requested by Neo and what is their respond of 2) confirmed ETA
is there any FPA changes not follow the lead time or increase of vol and trigger you need more as i noticed only Rapid relifef needed this .
Jul and Aug is their summer plant shut down as communciated earlier and therefore they can’t ship out by this timeframe . Have u contacted Honeywell to check if they can support any vol ? thanks